98000 Crore In Target For AAI and other Airport Developers

0

Upgradation/Modernisation of airports is a continuous process and is undertaken by Airports Authority of India (AAI) and other Airport Developers from time to time depending on the availability of land, commercial viability, socio-economic considerations, traffic demand / willingness of airlines to operate to/from such airports. AAI and other Airport Developers have targeted capital outlay of approximately Rs. 98000 crore in airport sector in the next five years for expansion and modernising of existing terminals, new terminals and strengthening of runways, among other activities. Out of this, Rs. 60000 crore (approx.) has been allocated for development of existing airports and Rs. 38000 crore (approx.) has been allocated for establishment of new Greenfield airports.

Government of India (GoI) has accorded ‘In-Principle’ approval for setting up of 21 new Greenfield Airports and the total estimated project cost of these 21 Greenfield airport projects is more than Rs. 45,000 crore.

Out of these, 11 Greenfield airports viz. Durgapur, Shirdi, Kannur, Pakyong, Kalaburagi, Orvakal (Kurnool), Sindhudurg, Kushinagar, Itanagar, Mopa and Shivamogga have been operationalised.

PPP Airport Operators namely Delhi, Bengaluru, Hyderabad, Lucknow, Mangaluru, Guwahati, Ahmedabad, Jaipur and Trivandrum have undertaken upgradation/ renovation works at respective airports at a CAPEX of more than Rs. 35,000 crore.

The list of major upgradation projects undertaken by Airports Authority of India (AAI) is at Annexure.

The timelines for construction/ upgradation of airports depend upon various factors such as land acquisition, mandatory clearances, removal of obstacles, financial closure etc. by the respective airport developers. The nation-wide lockdown and other impacts of covid-19 pandemic e.g. demobilisation of manpower, discontinuation of supply chain etc. and unprecedented adverse weather conditions have been the main attributing factors for delaying the upgradation projects undertaken by AAI.

The responsibility of implementation of airport projects including funding of the projects rests with the concerned airport developer including the respective State Government (in case the State Government is the project proponent).

 

Major Ongoing Projects (Costing more than ₹ 150 Cr.)

       
               

SN

Airport

Name of the Project

Approved Cost
(₹ in Cr.)

       

1

Patna

Construction of New Domestic Terminal Building and other structures (Phase I and II) at Patna Airport.

1216.90

       

2

Port Blair

Construction of NITB and allied works at Port Blair airport

707.73

       

3

Kolkata

Construction Of ATC Tower And Technical Block At Nscbi Airport, Kolkata

458.00

       

4

Kolkata

Airside Capacity Enhancement at NSCBI Airport, Kolkata

389.71

       

5

Hollongi
(Itanagar)

Construction of New Green Field Airport at Hollongi, Itanagar, Arunachal Pradesh

645.63

       

6

Imphal

Construction of New Integrated Terminal Building, Control Tower Cum Technical Block, Apron, Link Taxiway and Associated works at Imphal Interntional Airport, Imphal

499.00

       

7

Gwalior

Expansion of Civil Enclave at Gwalior Airport

446.12

       

8

Leh

Construction of  New Terminal Building at Leh Airport

480.33

       

9

Dehradun

Construction of Domestic Passenger Terminal Building at Dehradun Airport

456.86

       

10

D.Block (Safdarjung Airport)

Construction of Combined Operational Offices for DGCA, BCAS, AAIB, AERA & AAI at Safdarjung Airport, New Delhi.

351.20

       

11

Ayodhya

Development of Ayodhya Airport.

242.14

       

12

Chennai

Modernization of Chennai Airport Phase.II

2467.00

       

13

Trichy

Upgradation of passenger Terminal Building and Air side facilities at Tiruchirappalli International Airport.

951.28

       

14

Vijayawada

Construction of NITB including associated works at Vijayawada Airport.

611.80

       

15

Tuticorin

Development of Tuticorin Airport

380.81

       

16

Chennai

Modification of Strom Water Drains in Operatinal Area at Chennai Airport

209.01

       

17

Hyderabad

Construction of Civil Aviation Research Organisation (Phase-I) at Begumpet Airport, Hyderabad

353.61

       

18

Surat

Development of Surat Airport

353.25

       

19

Pune

Construction of NITB, re.construction of old terminal bldg., modification of existing expanded terminal building at  civil enclave Pune

475.39

       

20

Hirasar

Construction of Greenfield Airport Hirasar, Rajkot

1405.00

       

21

Jabalpur

Upgradation of Jabalpur Airport to make it suitable for operation of AB- 320 type of aircraft.

412.24

       

22

Kolhapur

Extension of Runway With Blast Pad, RESA, Taxiway, Apron, GSE Area, Isolation Bay, New Domestic Terminal Building And Miscellaneous Works At Kolhapur Airprt.

255.68

       

23

Dholera

Development of New Greenfield Airport at Dholera, Ahmedabad (Gujarat)

1305.00

       

24

Goa

Extension of Existing Integrated Terminal Building & Allied Works at Goa Airport.

255.69

       

25

Tirupati

Extension and Strengthening/ Resurfacing of existing Runway 08/26 for Code-E type of Aircraftat Tirupati Airport,Tirupati

177.10