Kulgam: The District Development Commissioner (DDC) Kulgam, Dr. Bilal Mohi-Ud-Din Bhat today inspected several developmental projects and took stock of the pace and progress of these projects.
He inspected the work site of Aadigen Damhal bridge and took stock of pace and progress made on it.
It was informed that the estimated project cost of this 7×42 meter span bridge is 20 crore and Girders on Six spans stands launched and completion date of this work project is March 2022.
The DDC, directed the Executing agency R&B to expedite the pace of work and engage additional men and machinery for early completion of the bridge which will benefit a huge population In the district.
Later he also inspected Residential quarters at Liroo Mirhama and took stock of progress of work on it.
The DDC directed all the concerned to scale up the pace of work on all the work projects across district that are under execution of various executing agencies for their early completion.