The Government provides financial and technical including skilling support under various schemes being implemented by the Ministry of New and Renewable Energy (MNRE) for development and promotion of new and renewable energy in all the states/UTs of the country, including State of Tamil Nadu. The details of Central Financial Assistance (CFA) provided under the various schemes are given in Annexure.
The government launched the PM Surya Ghar: Muft Bijli Yojana on 13.02.2024. One of its components involves the saturation of Government buildings with rooftop solar. Operational guidelines, issued on 03.07.2024, delineate the roles of various stakeholders in ensuring the saturation of Government buildings at both the Central and State levels under the Scheme. Further, as informed by the TANGEDCO (Tamil Nadu Generation and Distribution Corporation), the Tamil Nadu Energy Development Agency (TEDA) is implementing the solarization of Government buildings across the State of Tamil Nadu by installing rooftop solar under the CAPEX mode. This initiative specifically targets Government offices, court complexes, State-run industrial units, and educational institutions. As per the information received from Central Electricity Authority (CEA), the total Renewable Energy (RE) electricity generation in Tamil Nadu during the last five years and the current year is as under:
|
MJPS/SK
Annexure
Incentives being provided as Central Financial Assistance (CFA) for the implementation of major Renewable Energy Schemes/Programmes
Scheme/Programmes | Incentives presently available as per the Scheme | ||||||||||||||||||||
a) PM Surya Ghar: Muft Bijli Yojana | The details of the CFA pattern for the component “CFA to Residential Consumers” under this scheme are as follows:
|
||||||||||||||||||||
b) Central Public Sector Undertaking (CPSU) Scheme Phase-II (Government Producer Scheme) for grid-connected Solar Photovoltaic (PV) Power Projects by the Government Producers | Viability Gap Funding (VGF) support up to Rs. 55 lakhs per MW to the CPSUs/Govt. Organizations entities selected through competitive bidding process.
|
||||||||||||||||||||
c) PLI Scheme ‘National Programme on High Efficiency Solar PV Modules’ | The beneficiaries are eligible for Production Linked Incentive (PLI) on production and sale of solar PV modules. The quantum of PLI eligible for disbursal depends upon:
|
||||||||||||||||||||
d) Solar Park Scheme
|
(a) Up to Rs. 25 lakhs per Solar Park, for preparation of Detailed Project Report (DPR).
(b) Rs. 20 lakh per MW or 30% of the project cost, whichever is lower, for development of infrastructure. |
||||||||||||||||||||
e) PM-KUSUM scheme | Component A: Setting up of 10,000 MW of Decentralized Ground/Stilt Mounted Solar Power Plants
Benefits available: Procurement Based Incentive (PBI) to the DISCOMs @ 40 paise/kWh or Rs.6.60 lakhs/MW/year, whichever is lower, for buying solar power under this scheme. The PBI is given to the DISCOMs for a period of five years from the Commercial Operation Date of the plant. Therefore, the total PBI payable to DISCOMs is up to Rs. 33 Lakh per MW.
Component B: Installation of 14 Lakh Stand-alone Solar Pumps
Benefits available: CFA of 30% of the benchmark cost or the tender cost, whichever is lower, of the stand-alone solar agriculture pump is provided. However, in North Eastern States, Sikkim, Jammu & Kashmir, Ladakh, Himachal Pradesh, Uttarakhand, Lakshadweep and A&N Islands, CFA of 50% of the benchmark cost or the tender cost, whichever is lower, of the stand-alone solar pump is provided. Component B can also be implemented without State share of 30%. The Central Financial Assistance will continue to remain 30% and rest 70% will be borne by the farmer.
Component C: Solarisation of 35 Lakh Grid Connected Agriculture Pumps including through Feeder Level Solarisation
Benefits available:
(a) Individual Pump Solarization (IPS): CFA of 30% of the benchmark cost or the tender cost, whichever is lower, of the solar PV component will be provided. However, in North Eastern States, Sikkim, Jammu & Kashmir, Ladakh, Himachal Pradesh, Uttarakhand, Lakshadweep and A&N Islands, CFA of 50% of the benchmark cost or the tender cost, whichever is lower, of the solar PV component is provided. Component C (IPS) can also be implemented without State share of 30%. The Central Financial Assistance will continue to remain 30% and rest 70% will be borne by the farmer.
(b) Feeder Level Solarization (FLS): Agriculture feeders can be solarized by the State Government in CAPEX or RESCO mode with CFA of Rs. 1.05 Crore per MW as provided by MNRE. However, in North Eastern States, Sikkim, Jammu & Kashmir, Ladakh, Himachal Pradesh, Uttarkhand, Lakshadweep and Andaman & Nicobar Island, CFA of Rs. 1.75 crore per MW is provided.
|
||||||||||||||||||||
f) Green Energy Corridor Scheme
(for development of intra-state transmission system for RE projects) |
(a) GEC Phase-I: CFA of 40% of DPR cost or awarded cost whichever is lower.
(b) GEC Phase-II: CFA of 33% of DPR cost or awarded cost whichever is lower.
|
||||||||||||||||||||
g) Biomass Programme |
|
||||||||||||||||||||
h) Waste to Energy Programme | (a) For Biogas generation: Rs. 0.25 crore per 12000 cum/day (Maximum CFA- Rs.5 crore/project)
(b) For BioCNG/Enriched Biogas/Compressed Biogas generation: (Maximum CFA- Rs.10 crore/project) (i) BioCNG generation from new Biogas plant – Rs. 4 Crore per 4800 Kg/day; (ii) BioCNG generation from existing Biogas plant – Rs 3 Crore per 4800 Kg/day;
(c) For Power generation based on Biogas (Maximum CFA – Rs. 5 crore/project): (i) Power generation from new biogas plant: Rs. 0.75 crore per MW (ii) Power generation from existing biogas plant: Rs. 0.5 crore per MW
(d) For Power generation based on bio & agro-industrial waste (other than Municipal Solid Waste (MSW) through incineration process): Rs.0.40 crore/MW (Maximum CFA – Rs.5.00 Crore/Project)
(e) For Biomass Gasifier for electricity/ thermal applications:
Note:
|
||||||||||||||||||||
|
(a) Rs. 9800/- to Rs. 70,400/- per plant based on size of the plant in cubic meter for small biogas plants (1-25 cubic meter/day plant capacity)
(b) Rs. 35,000/- to Rs. 45,000/- per kilowatt for power generation and Rs. 17,500 /- to Rs. 22,500/- per kilowatt equivalent for thermal applications (25 – 2500 cubic meter/day plant capacity)
The eligible CFA would be 20% higher than Standard CFA in for North Eastern Region (NER), Island, Registered Gaushalas and SC/ST beneficiaries |
||||||||||||||||||||
j) R&D programme | The Ministry encourages research and technology development proposals in collaboration with the industry and provides up to 100% financial support to Government/non-profit research organizations and up to 70% to Industry, Start-ups, Private Institutes, Entrepreneurs and Manufacturing units. | ||||||||||||||||||||
k) National Green Hydrogen Mission | The Strategic Interventions for Green Hydrogen Transition (SIGHT) Programme guidelines under the Mission have been notified for Electrolyser Manufacturing and Mode-1, Mode 2A and Mode 2B for Green Hydrogen Production.
(a) SIGHT programme for Electrolyser manufacturing has an allocation of Rs. 4440 crore by 2029-30. The incentives start from Rs. 4440 per kW in the first year and end at Rs. 1480 per kW in the fifth year.
SIGHT programme for Green Hydrogen production (Mode-1) provides incentives for Green Hydrogen production, which are capped at Rs. 50/kg, Rs. 40/kg and Rs. 30/kg for the first, second and third year respectively.
For Mode 2A and 2B, the incentives are fixed at Rs. 50/kg, Rs. 40/kg and Rs. 30/kg for the first, second and third year respectively
(b) Pilot projects for projects in Mobility sector have an outlay of Rs. 496 crore.
(c) Pilot projects in Shipping sector have an outlay of Rs. 115 crore.
(d) Pilot projects in Steel sector have an outlay of Rs. 455 crore.
(e) Hydrogen hubs have been allocated an outlay of Rs. 200 crore.
(f) The R&D program of the Mission has a budget of Rs. 400 crore.
(g) Skill Development component of the Mission has an outlay of Rs. 35 crore.
(h) The Testing component of the Mission has an outlay of Rs. 200 crore. |